Client introduction: Petrochem Solutions provides a comprehensive offer including the design and manufacturing of Process Furnaces; Waste heat recovery units as well as process feasibility studies and other services.
We(Nuo Ou) perform whole project quality control and the inspectors on behalf of client to carried out inspection as per client’s ITP .
>> Pre-inspection meeting with manufacturer to clear production content, detail inspection scope and inspection arrangement.
>> Raw material arriving inspection including goods surface quality, quantity verify and randomly dimensional inspect.
>> Material cutting inspection as per client’s specification.
>> Reviewed WPS and welder ID prior to fabrication.
>> Fabrication process inspection such as fit-up gap, root face quality of super duplex pipe and welding parameter monitor as per WPS.
>> Randomly visual inspection for welds to verify whether brushed work has been done for each welds layer and tack weld quality.
>> Calibration certificates validity date verify for inspection tools and test meter which to be used while inspection and test.
>> Dimensional inspection including general length, holes distance, diameter for pipes, wall thickness, flange size, flange horizontal and perpendicularity, pipes fit-up angle in according to client’s specification and related standard.
>> Penetration test process witness for butt weld and welded tee.
>> Pickling and passivation inspection for super duplex pipes after welding.
>> Pressure test process witness for header.
>> Cleanliness and roughness inspection after skid frame sandblasting.
>> Environment condition such as ambient temperature, humidity and dew point while painting.
>> Sandpaper rough inspect for each layer painting and DFT check for primer,intermediate and top coating.
>> Final H point assembly inspection after pressure vessel, header, RO piping, grating, handrail, bracket, ERI and accessory parts installed in according to general arrangement drawing provided by client.
>> Bolts tightness and torque inspection. Torque reports and alignment reports reviewed as per ITP specified.
>> Packaging inspection and truck loading witness.
>> Expediting as per client’s progress and coordinate with manufacturer.
>> Punch list raised while non conformity issues were detected and push manufacturer to addressed them ASAP.
>> Daily reports submitted and final MDR review.